Construction of Sēlija military training area could cost twice as much – Kučinskis points to an alternative solution

New macroeconomic forecasts have raised the possibility that funding for the construction of the Sēlija military training area may not need to be secured outside the state budget, Finance Minister Māris Kučinskis (United List), who will lead the United List parliamentary group in the new Saeima, told the LETA news agency in an interview.

If the European Union’s statistical office, Eurostat, does not allow a public-private partnership (PPP) project to be accounted for outside the budget deficit, the PPP solution would be extremely expensive, Kučinskis said.

He explained that although payments could be spread over a longer period, the project itself would ultimately cost twice as much.

“This will be a major decision. I assume the government will still have to discuss it, as the Ministry of Defence has already prepared an information report.

“At present, Eurostat is showing no willingness to make concessions. Lithuania has already received a rejection. We essentially learned from their experience,” Kučinskis said.

The minister explained that a PPP arrangement is, in some respects, similar to taking out a mortgage because the necessary funds are not immediately available.

In Kučinskis’s view, if sufficient resources can be made available within the state budget and economic growth increases government revenue, it is necessary to assess whether taking on such financing at extremely high interest costs is worthwhile.

Asked whether the military training area could therefore most likely be financed directly from the defence budget, Kučinskis declined to make a prediction at this stage.

The minister explained that considerable work had already been carried out with the European Investment Bank and that a decision would have to be made.

“The Ministry of Defence is considering a PPP arrangement, but until now it has not had the opportunity to balance the budget.

“With the new forecasts, we can demonstrate that the project could also be implemented within the state budget by spreading the expenditure over several years.

“In any case, it will not be built in less than four or five years,” Kučinskis said.

Previously, TV3’s investigative programme “Nekā personīga” reported that the financing plan for the new military base and army storage facilities at the Sēlija training area remained unclear.

The facilities were originally intended to be built using private financing under a PPP model, with the state making payments over many years.

This arrangement was intended to allow the expenditure to remain outside the state budget.

However, Eurostat has prohibited the use of a similar arrangement for a project in Lithuania.

If the same decision is made regarding Latvia, and expenditure on the Sēlija military training area must already be included in the planned defence spending allocation of 5% of gross domestic product (GDP), other military development plans may have to be significantly slowed down.